Ocotillo Wind Energy Facility Project
CACA-51552

Environmental and Construction Compliance Monitoring Program

NOTE: This website is hosted by Dudek and is not an official BLM website. Linked files presented on this page are in PDF format. To view them, you will need to download the free Adobe Acrobat Reader if it is not already installed on your computer. For faster results in displaying the larger files, right-click the file's link, click "Save Target As" to download the file to your hard drive, then double-click the downloaded file.

 
 
 

Welcome to the Environmental and Construction Compliance Monitoring Program website for the Ocotillo Wind Energy Project (OWEF). The Bureau of Land Management (BLM) issued a Record of Decision approving the project on May 11, 2012 and issued the right-of-way (ROW) grant on May 11, 2012.

An Environmental and Construction Compliance Monitoring Program (ECCMP) was prepared for the project. The plan addresses the requirement to develop an environmental and construction monitoring plan for the project covering both construction and operation. This site has been established to track construction and monitor progress and completion of the mitigation goals established in the project's Environmental Impact Statement (EIS) and stipulations in the ROW grant.

Quick Links

Background

Operations and Maintenance Updates

Contact Information During Construction

Construction Progress and Environmental and Construction Compliance Reporting

For Additional Information

Background

Ocotillo Express (OE) LLC submitted an application for a ROW authorization to construct, operate, maintain, and decommission, an approximate 12,484-acre, up to 465-megawatt (MW) wind energy facility in western Imperial County on October 8, 2009. The application included up to 155 wind generating turbines, a substation, switchyard, administration, operations and maintenance facilities, transmission, and temporary construction lay down areas.

On May 11, 2012, the BLM issued a ROW grant to OE LLC to construct, operate, maintain, and decommission an up to 315 MW wind energy project (Ocotillo Wind Energy Facility Project) and its ancillary facilities on 10,151 acres of public lands near the town of Ocotillo, Imperial County, California. The project components to be developed on public lands include up to 112 wind turbines, a project substation/switchyard, an operations and maintenance building, access roads, underground collector cable system, and onsite permanent radar and up to three meteorological towers.  Also included are the following temporary construction facilities: parking/staging area/connex storage areas, construction laydown area, and a temporary pond.

Operations and Maintenance Updates

Notice of Temporary Suspension of Operations – November 22, 2016

Notice of Temporary Suspension of Operations – September 20, 2021

Acceptance of Return to Service Plan

Notice of Lifting of Temporary Suspension of Operations – January 27, 2023

Contact Information During Construction

BLM El Centro Field Office: 760-337-4400
Imperial County Air Pollution Control District: 760-482-4606
Imperial County Planning & Development Services: 760-482-4236
Project email: ocotillowindfacility@dudek.com
(Please note that email and attachment size limit is 10MB)

Construction Notices

Notice of Intent to Commence Construction - May 4, 2012

Notice of Intent to Commence Construction - Update - May 21, 2012

Construction Progress and Environmental Compliance Reporting

The BLM, in conjunction with OE LLC drafted an Environmental and Construction Compliance Monitoring Plan (ECCMP) to ensure compliance with mitigation measures approved in the Final EIS/EIR, as well as with the terms and conditions associated with the BLM ROW grant. Although changes may be made to the document as construction progresses, a current version of the ECCMP document and attachments is found here. The regional vicinity map and project location map depict the location of the project.

Notice to Proceeds (NTP's)

Issuance of NTPs will be contingent upon OE LLC’s compliance with pre-construction requirements as specified by the approved mitigation measures and responsible agency permitting requirements. Approved pre-compliance reports, permit applications, and other documents are available in their final form here. NTPs that have been issued to OE LLC are noted in the table below.

Notice to Proceed Construction Activities NTP Request Submitted NTP Issued
1

Construction of the following components:

  • 12-acre temporary laydown yard
  • 30-acre Substation/Switchyard
  • Temporary and permanent access road and electrical collection system
  • Temporary and permanent areas for 71 turbines (see Exhibit attached to NTP request)
  • Geotechnical activities
  • Facility improvements at the SDG&E Energy switchyard
April 27, 2010 May 14, 2012

Figure 1. NTP-1 conditions
2

Construction of the following facilities:

  • Temporary and permanent turbine area for all 112 turbines.
  • Temporary and permanent areas for 2 MET towers
  • 3.4-acre O&M facility
  • 10-acre temporary laydown area
  • Temporary connex storage areas
  • Temporary crane walk corridors
  • Excavation and installation for all project infrastructure including foundations, collection system, electrical utility, and communication systems.
  • Structural erection for all approved project features including concrete foundations, structural steel, wind turbine towers, MET towers, and the wind farm substation.
  • Electrical wiring, testing, and pre-commissioning of wind turbines, MET towers, collection electrical system and wind farm substation.
  • Construction of all buildings and associate facilities including the O&M building, biological observation tower, control buildings at substation and switchyard.
  • Structure installation at the SDG&E energy switchyard.
June 8, 2012 June 27, 2012
3 Commercial Operation
  • Operation and maintenance of the Ocotillo Express Wind Facility
November 27, 2012 December 21, 2012

Environmental Monitoring Reports

A BLM Environmental Monitor (EM) will monitor construction activities to ensure that they are conducted in accordance with the approved mitigation measures and permit conditions. Monthly reports documenting construction status and compliance activities are posted here.

Variance Requests

As defined by the ECCMP, at various times throughout project construction, the need for extra workspace or additional access roads may be identified. Similarly, changes to the project requirements (e.g., mitigation measures, specifications, etc.) may be needed to facilitate construction or provide more effective protection of resources (e.g., installation of additional erosion control outside of approved disturbance areas). The BLM Project Manager, along with the BLM EMs, will implement the variance procedures defined in the ECCMP to evaluate each proposed project variance for its potential for creating adverse environmental effects to determine whether supplemental NEPA review is required. Variance requests are posted here.

Approval Documents

Record of Decision

Right-of-Way Grant

For Additional Information

For inquiries or to request additional information or to be added to the mailing list, please contact us by phone, fax, or email as follows:


BLM El Centro Field Office: 760-337-4400
Imperial County Air Pollution Control District: 760-482-4606
Imperial County Planning & Development Services: 760-482-4236
Project email: ocotillowindfacility@dudek.com
(Please note that email and attachment size limit is 10MB)

BLM Project Manager:

Carrie Sahagun
Bureau of Land Management
El Centro Field Office
1661 S. 4th Street
El Centro, CA 92243
Phone: 760-337-4437
Email: csahagun@blm.gov

This page contains tables and is best viewed with Netscape or Internet Explorer. Please report any problems to the web coordinator.

  Related Links:

   
replica watches uk
replica watches sale
replica watches
hublot replica